The top floor where the plant room is located is still under construction. The services on the roof are to be housed in a portal frame type structure. Concrete slabs where being installed as well as the structural elements for the frame.
Concrete is being poured to form a slab. In this photo the void barrier can be seen as well as the reinforment which is sitting on reinforment chairs. The concrete is currently beng placed and will be poured to the level of the surrounding formwork. The process of installing the slab is in this order.
This slab itself is actually a floating slab and has metal casting mounts with rubber inside (the red mounts in photo). Bolts are screwed through the metal casting into the rubber mount which then raises the slab.
Services such as generators, chillers, pumps are positioned on top of the floating floor. Having the floor raised on rubber mounts eliminates sound travelling through the building. Floating floors are used when acousitc solutions to vibration are required.Here the slab is still being poured. Shovels are used to move the concrete around and a worker uses a piece of timber to smooth out the concrete.