Monday, May 21, 2007
Glen Waverley Medical Consulting Suite
AXA / Grocon Site
The top floor where the plant room is located is still under construction. The services on the roof are to be housed in a portal frame type structure. Concrete slabs where being installed as well as the structural elements for the frame.
Concrete is being poured to form a slab. In this photo the void barrier can be seen as well as the reinforment which is sitting on reinforment chairs. The concrete is currently beng placed and will be poured to the level of the surrounding formwork. The process of installing the slab is in this order.
This slab itself is actually a floating slab and has metal casting mounts with rubber inside (the red mounts in photo). Bolts are screwed through the metal casting into the rubber mount which then raises the slab.
Services such as generators, chillers, pumps are positioned on top of the floating floor. Having the floor raised on rubber mounts eliminates sound travelling through the building. Floating floors are used when acousitc solutions to vibration are required.Here the slab is still being poured. Shovels are used to move the concrete around and a worker uses a piece of timber to smooth out the concrete.
Friday, May 18, 2007
Building and Construction Links
www.multiplex.com.au
www.grocon.com.au
www.salta.com.au
www.onesteel.com
www.bh.com.au
www.boralbricks.com.au
www.moenglass.com.au
www.stilcon.com.au
www.waa.net.au
www.bonaccigroup.com
www.hansenyuncken.com.au
Thursday, May 17, 2007
Bovis Lend Lease, C3 C4 Site Visit
Concrete tilt-up panels have been lifted by a mobile crane into position. Chemset bolts have been installed in the concrete panel and slab. A strut or temporary brace is fixed to the slab and wall until other structural elements have been installed and the wall can safely be unbraced.
Chemset bolts nuts are removed followed by the brace. The remaining bolt in the slab can be hit with a hammer so that it dissapears into the slab and later the hole can filled with concrete. Formwork is used to shape and mould the concrete to the desired shape. When the concrete has reached th MPa specified by the structural engineer the formwork can be removed.
This formwork has a plywood face to make the concrete finish smooth. A top and bottom kicker with studs in between have also been used. A brace has also been used to help resist pressure from the concrete. The underside of the formwork consists of a bearer which supports a joist and joist which suports the plywoof base.
Reinforcement for the slab has been installed by steel workers. Vertical bars are also in place awaiting the installation of the columns.
The lift shaft or core of this building is erected first. The core is used to stiffen the struture and all floors will be fixed to it.
Construction Process Selected
The above detail from Bonacci Group is the construction process which I have selected for the major assignment. It shows a universal column with base plate attached to a pad which is located on the perimeter wall of the warehouse. It also shows the slab and reinforcement method that would be used. My model and poster are based on this detail.